Industrial Engineering - Based Productivity & Layout Optimization: A Case Study
Industrial EngineeringCompleted
2026

Industrial Engineering - Based Productivity & Layout Optimization: A Case Study

Individual Project - Asiri Sandakelum

Layout Optimization
Productivity Improvement
Process Mapping
Inventory Strategy

01 — Overview

Optimized assembly and inspection processes at the Hero Motorcycle Assembly Plant using facility layout improvements, material handling reduction, and safety-focused test track design.

02 — Problem Statement

Suboptimal layout, bidirectional movement paths, shared-road testing, and reactive WIP management limited throughput and raised safety risks.

03 — Objectives

  • 01Optimize assembly and inspection flow for higher plant productivity
  • 02Reduce material handling waste and eliminate dead-end workstations
  • 03Establish a dedicated drive-through test track and safer workflow
  • 04Implement strategic safety stock to reduce WIP delays

04 — Key Outcomes

Identified PDI/QC as primary constraints with 75 minutes/unit

Reduced material search waste by 90 minutes per batch

Proposed a drive-through workstation layout and standalone test track

Developed a data-driven inventory strategy for stable throughput

05 — Tools & Technologies

Shop-floor observationProcess MappingLayout OptimizationInventory Strategy